Thursday, February 2, 2017

Friday, January 20, 2017

Roof trusses and roof deck

The roof deck and roof trusses are on.  There will be some bodacious parties on that deck!  There will be a couple of rooms carved out of the roof trusses.  Possibly a man cave?
Photo was shot with a DJI Phantom 3 standard drone that Santa brought.

Friday, December 9, 2016

2nd Floor Walls

 The walls are 6" thick, cast-in-place concrete.  There are over 200 tons of concrete in the walls!
~110 cubic yards
The 2nd floor walls are up and the view is amazing!

This is a view from the living room.  The glass opening is 24 feet wide!  The concrete forms will come off soon.

Sunday, November 13, 2016

Concrete Walls


The first floor concrete walls have been poured.  Check out the view from the first floor.  I can't wait to see the second floor view!

Wednesday, October 26, 2016