Wednesday, October 26, 2016

Walls Started

As soon as the concrete was poured, they started placing the steel for the concrete walls.

Foundation complete


The foundation finally got poured.  They used a 32 meter boom pump to place the concrete.  The foundation has 73 yards of concrete.

And a Hurricane

There have been some minor delays.  The plumber was busy and it took a while before we could get the rough plumbing completed.  Then hurricane Matthew blasted through.  We stopped work and secured everything.  There was no damage to the property, though there was a lot of beach erosion.  Finally, the concrete guys could finish the foundation.