The pilings were drilled today. There are 28 continuous flight auger piles. The piles are 16 inches in diameter and 30 to 35 feet deep. It is amazing to see how they install these! They drill a hole to the pile depth with a hollow auger, then pump concrete under pressure through the drill. As the auger is removed concrete is pumped to the top of the hole. Then a steel reinforcing cage is lowered into the wet concrete.
Showing posts with label dirt. Show all posts
Showing posts with label dirt. Show all posts
Tuesday, August 30, 2016
Pilings
The pilings were drilled today. There are 28 continuous flight auger piles. The piles are 16 inches in diameter and 30 to 35 feet deep. It is amazing to see how they install these! They drill a hole to the pile depth with a hollow auger, then pump concrete under pressure through the drill. As the auger is removed concrete is pumped to the top of the hole. Then a steel reinforcing cage is lowered into the wet concrete.
Labels:
auger,
auger piles,
beach,
beachfront,
beachfront home,
build,
building,
concrete,
construction,
dirt,
drill,
fill,
FL,
florida,
install,
installation,
pilings,
steel,
steel reinforcing cage,
video
Tuesday, August 23, 2016
Gold Dust
We brought in 14 loads of fill today. The dirt has to be approved as compatible with the existing beach dune sand. Therefore, the stuff is trucked in from Vero Beach and costs like it is flecked with gold!